Boiler House Installation of Metric Tru-Bore Pipework
Fabrication, Supply, and Installation of 316l Metric Tru-Bore Pipework
ShawPF were awarded the Pipework Package on an upgrade to an existing energy centre, including the Pre-Fabrication, Welding, Site Installation and testing of all Pipework services.
Scope of Work
- Pipework Supply and Installation
We fabricated and installed high-quality Metric Tru-Bore pipework with full traceability to meet the client’s requirements. - Pressure Testing
We pressure-tested the pipework system to guarantee reliability and safety.
- Quality Assurance
Conducted 100% weld inspections by our CSWIP-certified welding inspector. Completed 10% Dye Penetrant Inspections (DPI) to ensure weld integrity. - Equipment Installation
As part of the project, we installed Ground Source Heat Pumps, Electric Boilers, and Plate Heat Exchangers.
Challenges
The project was delivered with full Quality Assurance pack, including; Weld Maps, NDT Reports, Pressure Testing and full Material Traceability.
Prefabricated Pump Skids Gallery








How We Delivered
- Off-Site Fabrication
We used our advanced workshop to pre-fabricate the pipework to precise measurements. This reduced the time required on-site and ensured flawless quality.
- On-Site Installation
Our skilled team installed the fabricated components efficiently, working closely with the client to maintain smooth project delivery.
- Ensuring Top Standards
With full material traceability, rigorous inspections, and thorough pressure testing, we delivered a system that was fully compliant and ready to perform from day one.
Results
We completed the boiler house installation on schedule, delivering a high-performing system tailored to the client’s needs. The quality of our fabrication, installation, and testing ensured that everything was operational and exceeded expectations upon commissioning.